How Long Does a House Extension Take to Build?

February 2025·5 min read

One of the most common questions we hear is "How long will my extension take?" Here's a realistic breakdown — from the initial idea through to moving the furniture in.

The Full Timeline

1. Design & Drawings

2–4 weeks

Architectural drawings, structural engineer calculations, and design decisions.

2. Planning Permission (if needed)

8–10 weeks

From submission to decision. Not all projects need this — many fall under Permitted Development.

3. Building Regulations Submission

2–4 weeks

Submitting detailed plans for Building Control approval. Can run in parallel with planning.

4. Contractor Booking & Preparation

2–6 weeks

Good builders are booked in advance. We typically have a 4–8 week lead time.

5. Construction

See below

The actual build time depends on the type and size of extension.

Build Times by Extension Type

Single-storey rear extension (small)8–12 weeks
Single-storey rear extension (large / prior approval)12–16 weeks
Double-storey extension14–22 weeks
Wrap-around extension14–20 weeks
Garage conversion3–5 weeks
Loft conversion6–10 weeks

What Can Cause Delays?

Bad weather — particularly during groundworks and roofing stages

Planning delays — if the council requests amendments or neighbours object

Material supply issues — especially for bespoke items like bifold doors or steelwork

Client changes mid-build — changes to the specification once work has started

Unexpected ground conditions — poor soil, underground services, or contamination

How We Keep Things on Track

We provide a detailed programme of works before we start, with clear milestones and weekly updates. Our project management approach means you always know what's happening, what's next, and when to expect completion. With 45+ years of experience, we know how to plan for the unexpected and keep your build moving.